Assessment Year | 2019 |
---|---|
Principal Product | Water |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 4941: Water Supply |
Sales Range | $10 M to 50M |
# of Employees | 23 |
Plant Area |
1,045,440
ft2
|
Annual Production | 1,700,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $102,022 | 1,373,568 |
kWh
|
$0.074 |
Electricity Demand | $12,846 | 3,211 |
kW-mo/yr
|
$4.00 |
Electricity Fees | $(-12,971.4) | - |
|
- |
TOTAL YEARLY COSTS | $101,897 | |||
RECOMMENDED SAVINGS* | $493,161 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,577 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Usage Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,893 | $2,389 |
$1,893
22,645
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,060 | $1,959 |
$2,060
24,642
kWh
|
- | |
03 | 2.7135: Install occupancy sensors | $1,234 | $616 |
$1,234
14,759
kWh
|
- | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $1,095 | $3,250 |
$1,095
13,097
kWh
|
- | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,388 | - |
$1,388
16,606
kWh
|
- | |
06 | 3.7311: Maintain machines to reduce leaks | $1,094 | $844 | - |
$1,094
-
Tgal
|
|
07 | 3.8121: Cover containers to minimize evaporative losses | $483,876 | $1,077,133 | - |
$483,876
-
Tgal
|
|
08 | 2.7423: Reduce heat gain by window tinting | $520 | $483 |
$520
6,217
kWh
|
- | |
TOTAL RECOMMENDED | $493,161 | $1,086,674 |
$8,190
97,965
kWh
|
$484,971
-
Tgal
|
||
TOTAL IMPLEMENTED | $3,577 | $4,094 |
$2,483
29,703
kWh
|
$1,094
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs