ITAC Assessment: TR0009
ITAC logo
ITAC Assessment: TR0009
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Breakers and Switches
NAICS 335313: Switchgear and Switchboard Apparatus Manufacturing
SIC 3613: Switchgear and Switchboard Apparatus
Sales Range $1
M
to 5
M
# of Employees 77
Plant Area 64,614
ft2
Annual Production 104,000,000
pieces
Production Hrs. Annual 2,400
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $128,803 1,180,560
kWh
Electricity Demand $3,042 517
kW-mo/yr
Natural Gas $4,800 523
MMBtu
Waste Disposal Costs
Water Usage $3,587 810,000
Tgal
TOTAL YEARLY COSTS $140,232
RECOMMENDED SAVINGS* $32,484 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,910

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Fees Savings
01 2.3212: Optimize plant power factor $3,043 $12,500 $3,043
02 3.5318: Recycle fluorescent lamps $6,608 $13,260 $6,608
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $814 - $814
04 2.7425: Clean or color roof to reduce solar load $2,987 $15,373 $2,987
05 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $17,718 $3,748 $17,718
06 4.652: Replace existing equipment with more suitable substitutes $1,315 $14,000 $1,315
TOTAL RECOMMENDED $32,484 $58,881 $32,484
TOTAL IMPLEMENTED $10,910 $42,633 $10,910
Yearly Savings* Imp'd Cost* Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs