ITAC Assessment: TP0017
ITAC logo
ITAC Assessment: TP0017
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Sliding and swinging metal doors
NAICS
n/a
SIC 3429: Hardware, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 60,000
pieces
Production Hrs. Annual 3,937
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,374 1,956,330
kWh
Electricity Demand $37,423 5,626
kW-mo/yr
Natural Gas $23,972 9,317
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,923 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.8123: Pay utility bills on time $9,916 $9,916 - - - $9,916
02 2.7124: Make a practice of turning off lights when not needed $4,685 $2,056 $4,685
149,179
kWh
- - -
03 2.2511: Insulate bare equipment $3,519 $1,745 - - $3,519
-
MMBtu
-
04 2.7124: Make a practice of turning off lights when not needed $2,327 - $1,054
35,463
kWh
$1,273
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,803 $14 $1,068
33,998
kWh
$735
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $1,911 $1,759 $1,911
60,961
kWh
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,423 $280 $912
29,045
kWh
$511
-
kW-mo/yr
- -
08 2.4314: Use synthetic lubricant $701 - $387
12,310
kWh
$314
-
kW-mo/yr
- -
09 2.4133: Use most efficient type of electric motors $587 $5,219 $336
11,723
kWh
$251
-
kW-mo/yr
- -
10 2.7124: Make a practice of turning off lights when not needed $1,026 $230 $595
19,050
kWh
$431
-
kW-mo/yr
- -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $310 - $177
5,569
kWh
$133
-
kW-mo/yr
- -
12 2.7124: Make a practice of turning off lights when not needed $715 - $715
22,567
kWh
- - -
TOTAL RECOMMENDED $28,923 $21,219 $11,840
379,865
kWh
$3,648
-
kW-mo/yr
$3,519
-
MMBtu
$9,916
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs