ITAC Assessment: TP0016
ITAC logo
ITAC Assessment: TP0016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Steel nursing home, dormitory and detention furniture
NAICS
n/a
SIC 2531: Public Building and Related Furniture
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area
n/a
Annual Production 92,226
pieces
Production Hrs. Annual 4,335
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $175,954 4,773,740
kWh
Electricity Demand $68,746 10,245
kW-mo/yr
Natural Gas $66,026 25,600
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,900 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,503

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7224: Reduce space conditioning during non-working hours $8,751 $5,000 $8,751
278,722
kWh
- -
02 2.7124: Make a practice of turning off lights when not needed $4,037 - $2,615
72,685
kWh
$1,422
-
kW-mo/yr
-
03 2.2511: Insulate bare equipment $2,307 $1,326 - - $2,307
-
MMBtu
04 2.7124: Make a practice of turning off lights when not needed $2,278 - $2,278
72,685
kWh
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,733 $20 $1,068
33,998
kWh
$665
-
kW-mo/yr
-
06 2.7135: Install occupancy sensors $1,456 - $1,456
46,307
kWh
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,423 $280 $912
29,015
kWh
$511
-
kW-mo/yr
-
08 2.4314: Use synthetic lubricant $595 - $348
11,430
kWh
$247
-
kW-mo/yr
-
09 2.4133: Use most efficient type of electric motors $613 $6,187 $344
10,844
kWh
$269
-
kW-mo/yr
-
10 2.7124: Make a practice of turning off lights when not needed $373 - $373
10,258
kWh
- -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $334 - $201
6,448
kWh
$133
-
kW-mo/yr
-
TOTAL RECOMMENDED $23,900 $12,813 $18,346
572,392
kWh
$3,247
-
kW-mo/yr
$2,307
-
MMBtu
TOTAL IMPLEMENTED $19,503 $6,606 $15,130
469,813
kWh
$2,066
-
kW-mo/yr
$2,307
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs