ITAC Assessment: TN0692
ITAC logo
ITAC Assessment: TN0692
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product distribution switch gear
NAICS
n/a
SIC 3629: Electrical Industrial Apparatus, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 630
Plant Area 360,000
ft2
Annual Production 8,100
pieces
Production Hrs. Annual 6,500
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $201,962 7,552,755
kWh
Electricity Demand $206,012 16,716
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,545,631 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $914,911

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 4.453: Reschedule breaks to allow for continuous production $3,613,000 $645,000 - - $18,000 - $3,595,000
02 4.451: Add additional production shift $899,000 $967,000 - - - - $899,000
03 2.2437: Recover waste heat from equipment $10,500 $700 $10,500
1,190,211
kWh
- - - -
04 2.3191: Use demand controller or load shedder $7,220 $11,900 - $7,220
-
kW-mo/yr
- - -
05 3.5311: Recover and reuse waste material $4,210 - - - - $4,210
-
lb
-
06 2.6218: Turn off equipment when not in use $3,650 - $3,650
121,630
kWh
- - - -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,600 $900 - $3,600
-
kW-mo/yr
- - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $3,336 - $2,611
87,046
kWh
$725
-
kW-mo/yr
- - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,115 $1,300 $668
22,274
kWh
$447
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $4,545,631 $1,626,800 $17,429
1,421,161
kWh
$11,992
-
kW-mo/yr
$18,000 $4,210
-
lb
$4,494,000
TOTAL IMPLEMENTED $914,911 $969,200 $6,929
230,950
kWh
$4,772
-
kW-mo/yr
- $4,210
-
lb
$899,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs