| Assessment Year | 2000 |
|---|---|
| Principal Product | Cast aluminum wheels |
| NAICS |
n/a
|
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $50 M to 100M |
| # of Employees | 400 |
| Plant Area |
300,000
ft2
|
| Annual Production | 1,275,000
pieces
|
| Production Hrs. Annual | 7,344
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,210,739 | 40,669,696 |
kWh
|
$0.030 |
| Electricity Demand | $330,094 | 61,242 |
kW-mo/yr
|
$5.39 |
| Natural Gas | $1,442,080 | 480,040 |
MMBtu
|
$3.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $700,738 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $258,893 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $272,160 | $169,485 | - |
$272,160
-
MMBtu
|
- | - | - | - | |
| 02 | 4.445: Install equipment to move product | $164,990 | $183,505 |
$(-2,085.0)
54,807
kWh
|
- | - | - | $167,075 | - | |
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $93,903 | $3,930 |
$18,453
485,053
kWh
|
$175,695
-
MMBtu
|
- | - | $(-100,245.0) | - | |
| 04 | 2.8113: Purchase gas directly from a contract gas supplier | $72,100 | - | - |
$72,100
-
MMBtu
|
- | - | - | - | |
| 05 | 2.2531: Re-size charging openings or add movable cover or door | $29,370 | $9,805 | - |
$29,370
-
MMBtu
|
- | - | - | - | |
| 06 | 3.4111: Use closed cycle process to minimize waste water production | $32,000 | $13,020 | - | - |
$32,000
-
Tgal
|
- | - | - | |
| 07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $17,200 | $5,810 | - | - | - |
$16,000
-
lb
|
- | $1,200 | |
| 08 | 2.2437: Recover waste heat from equipment | $14,310 | $33,160 | - |
$14,310
-
MMBtu
|
- | - | - | - | |
| 09 | 2.2514: Cover open tanks | $4,705 | $2,280 | - |
$4,705
-
MMBtu
|
- | - | - | - | |
| TOTAL RECOMMENDED | $700,738 | $420,995 |
$16,368
539,860
kWh
|
$568,340
-
MMBtu
|
$32,000
-
Tgal
|
$16,000
-
lb
|
$66,830 | $1,200 | ||
| TOTAL IMPLEMENTED | $258,893 | $187,435 |
$16,368
539,860
kWh
|
$175,695
-
MMBtu
|
- | - | $66,830 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs