Assessment Year | 2000 |
---|---|
Principal Product | Acrylic Bath Tubs and Shower Stalls |
NAICS |
n/a
|
SIC | 3088: Plastics Plumbing Fixtures |
Sales Range | $5 M to 10M |
# of Employees | 40 |
Plant Area |
34,000
ft2
|
Annual Production | 8,750
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,951 | 443,142 |
kWh
|
$0.034 |
Electricity Demand | $10,391 | 1,732 |
kW-mo/yr
|
$6.00 |
Electricity Fees | $1,363 | - |
|
- |
Natural Gas | $12,660 | 1,691 |
MMBtu
|
$7.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,556 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,356 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.721: Initiate a program to acquire iso certification | $30,000 | $30,000 | - | - | - | - | $30,000 | |
02 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $7,356 | $5,625 | - | - | - |
$7,356
-
lb
|
- | |
03 | 3.5311: Recover and reuse waste material | $4,766 | $15,450 | - | - |
$4,766
-
gal
|
- | - | |
04 | 4.611: Begin a practice of predictive / preventative maintenance | $2,820 | $1,075 |
$120
3,517
kWh
|
- | - | - | $2,700 | |
05 | 2.3191: Use demand controller or load shedder | $1,440 | $3,180 | - |
$1,440
-
kW-mo/yr
|
- | - | - | |
06 | 3.5313: Increase amount of waste recovered for resale | $1,174 | $240 | - | - | - |
$1,174
-
lb
|
- | |
TOTAL RECOMMENDED | $47,556 | $55,570 |
$120
3,517
kWh
|
$1,440
-
kW-mo/yr
|
$4,766
-
gal
|
$8,530
-
lb
|
$32,700 | ||
TOTAL IMPLEMENTED | $7,356 | $5,625 | - | - | - |
$7,356
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs