ITAC Assessment: TN0676
ITAC logo
ITAC Assessment: TN0676
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Extruded plastic film
NAICS
n/a
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $10
M
to 50
M
# of Employees 215
Plant Area 160,000
ft2
Annual Production 63,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $688,378 18,538,101
kWh
Electricity Demand $263,532 28,269
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $164,277 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,891

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 4.431: Train operators for maximum operating efficiency $105,000 $94,080 - - - $105,000
02 4.122: Develop standard procedures to improve internal yields $37,314 $28,050 $34,200
777,257
kWh
- - $3,114
03 2.2623: Minimize condenser cooling water temperature $6,275 $18,200 $6,275
119,578
kWh
- - -
04 3.5316: Contract a wood pallet recycling company $6,144 $1,200 - - $6,144
-
lb
-
05 3.5217: Reuse / recycle/ sell paper products $4,496 $12,200 - - $4,290
-
lb
$206
06 2.6215: Shut off air conditioning in winter heating season $3,095 $6,250 $3,095
70,340
kWh
- - -
07 2.2136: Install / repair insulation on steam lines $1,025 $175 $709
16,120
kWh
$316
-
kW-mo/yr
- -
08 3.4155: Meter waste water $928 $2,300 - - - $928
TOTAL RECOMMENDED $164,277 $162,455 $44,279
983,295
kWh
$316
-
kW-mo/yr
$10,434
-
lb
$109,248
TOTAL IMPLEMENTED $14,891 $36,825 $10,079
206,038
kWh
$316
-
kW-mo/yr
$4,290
-
lb
$206
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs