| Assessment Year | 1999 |
|---|---|
| Principal Product | Uniforms |
| NAICS |
n/a
|
| SIC | 2326: Men's and Boys' Work Clothing |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
100,000
ft2
|
| Annual Production | 488,000
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $23,267 | 788,980 |
kWh
|
$0.029 |
| Electricity Demand | $13,515 | 3,908 |
kW-mo/yr
|
$3.46 |
| Electricity Fees | $6,329 | - |
|
- |
| Natural Gas | $42,738 | 6,593 |
MMBtu
|
$6.48 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $59,662 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $38,164 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.5313: Increase amount of waste recovered for resale | $30,906 | $3,200 | - | - | - |
$30,906
-
lb
|
- | |
| 02 | 4.322: Eliminate old stock and modify inventory control | $20,663 | $16,000 | - | - | - | - | $20,663 | |
| 03 | 2.7261: Install timers and/or thermostats | $6,283 | $3,000 |
$5,363
98,183
kWh
|
- |
$920
-
MMBtu
|
- | - | |
| 04 | 2.2531: Re-size charging openings or add movable cover or door | $640 | $1,250 |
$640
11,723
kWh
|
- | - | - | - | |
| 05 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $493 | $625 | - | - | - |
$493
-
lb
|
- | |
| 06 | 2.4314: Use synthetic lubricant | $342 | - |
$242
4,396
kWh
|
$100
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.6218: Turn off equipment when not in use | $335 | - |
$335
12,309
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $59,662 | $24,075 |
$6,580
126,611
kWh
|
$100
-
kW-mo/yr
|
$920
-
MMBtu
|
$31,399
-
lb
|
$20,663 | ||
| TOTAL IMPLEMENTED | $38,164 | $7,450 |
$6,338
122,215
kWh
|
- |
$920
-
MMBtu
|
$30,906
-
lb
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs