ITAC Assessment: TN0668
ITAC logo
ITAC Assessment: TN0668
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Corrugater cardboard containers
NAICS
n/a
SIC 2653: Corrugated and Solid Fiber Boxes
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 135,000
ft2
Annual Production 200,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $142,330 3,889,508
kWh
Electricity Demand $86,617 9,958
kW-mo/yr
Natural Gas $163,236 38,561
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $944,251 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $704,076

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings One-time Revenue or Avoided Cost Savings
01 3.1192: Reduce scrap production $674,570 $64,500 - - - - $729,000
-
lb
$(-23,870.0) $(-30,560.0) - -
02 4.211: Consider use / purchase of bulk materials where possible $238,000 $110,000 - - - - $221,000
-
lb
- - $17,000 -
03 2.3212: Optimize plant power factor $9,000 $26,000 - - $9,000 - - - - - -
04 3.5248: Separate and recycle scrap metal to foundry or for sale $7,860 $8,370 - - - - $7,860
-
lb
- - - -
05 4.421: Modify current incentive program $6,300 $1,200 - - - - - - $2,000 - $4,300
06 2.4231: Reduce the pressure of compressed air to the minimum required $2,696 - $1,325
38,980
kWh
$1,371
-
kW-mo/yr
- - - - - - -
07 2.2136: Install / repair insulation on steam lines $2,175 $1,280 $2,175
151,817
kWh
- - - - - - - -
08 3.4155: Meter waste water $1,120 $3,300 - - - $1,120
-
Tgal
- - - - -
09 2.2511: Insulate bare equipment $940 $540 $940
65,358
kWh
- - - - - - - -
10 2.2135: Repair and eliminate steam leaks $900 $196 $900
62,720
kWh
- - - - - - - -
11 2.6242: Minimize operation of equipment maintained in standby condition $690 - $690
20,223
kWh
- - - - - - - -
TOTAL RECOMMENDED $944,251 $215,386 $6,030
339,098
kWh
$1,371
-
kW-mo/yr
$9,000 $1,120
-
Tgal
$957,860
-
lb
$(-23,870.0) $(-28,560.0) $17,000 $4,300
TOTAL IMPLEMENTED $704,076 $104,106 $3,855
187,281
kWh
$1,371
-
kW-mo/yr
$9,000 $1,120
-
Tgal
$736,860
-
lb
$(-23,870.0) $(-28,560.0) - $4,300
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs