Assessment Year | 1999 |
---|---|
Principal Product | Military Parachutes |
NAICS |
n/a
|
SIC | 2399: Fabricated Textile Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
70,000
ft2
|
Annual Production | 14,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $46,845 | 569,754 |
kWh
|
$0.082 |
Electricity Demand | $17,896 | 3,660 |
kW-mo/yr
|
$4.89 |
Electricity Fees | $2,105 | - |
|
- |
Natural Gas | $53,157 | 10,130 |
MMBtu
|
$5.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $79,297 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,562 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7144: Install spectral reflectors / delamp | $6,379 | $13,600 |
$5,923
126,026
kWh
|
- | - | - | - | $456 | |
02 | 2.7145: Install skylights | $4,132 | $7,350 |
$4,132
87,925
kWh
|
- | - | - | - | - | |
03 | 3.5313: Increase amount of waste recovered for resale | $1,603 | $800 | - | - | - |
$103
-
lb
|
$1,500 | - | |
04 | 2.6218: Turn off equipment when not in use | $1,041 | - |
$496
10,551
kWh
|
- |
$545
-
MMBtu
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $992 | $750 |
$640
13,482
kWh
|
$352
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.5313: Increase amount of waste recovered for resale | $1,950 | $800 | - | - | - |
$450
-
lb
|
$1,500 | - | |
07 | 4.112: Replace old machine with new automatic multi-station tool | $56,000 | $161,000 | - | - | - | - | $56,000 | - | |
08 | 4.421: Modify current incentive program | $7,200 | $4,500 | - | - | - | - | $7,200 | - | |
TOTAL RECOMMENDED | $79,297 | $188,800 |
$11,191
237,984
kWh
|
$352
-
kW-mo/yr
|
$545
-
MMBtu
|
$553
-
lb
|
$66,200 | $456 | ||
TOTAL IMPLEMENTED | $17,562 | $19,650 |
$7,059
150,059
kWh
|
$352
-
kW-mo/yr
|
$545
-
MMBtu
|
$450
-
lb
|
$8,700 | $456 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs