ITAC Assessment: TN0661
ITAC logo
ITAC Assessment: TN0661
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Insulated copper wire
NAICS
n/a
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 140,000
ft2
Annual Production 40,000,000
lb
Production Hrs. Annual 6,600
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $410,414 12,597,011
kWh
Electricity Demand $280,110 34,725
kW-mo/yr
Electricity Fees $82,782 -
Natural Gas $3,177 426
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $496,319 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $200,438

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Gaseous Waste Savings Primary Product Savings
01 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $175,335 $5,000 - - - - - - $175,335
-
lb
-
02 4.445: Install equipment to move product $91,400 $49,760 - - - - - - - $91,400
03 3.5212: Regrind, reuse, or sell scrap plastic parts $73,031 $8,750 $(-1,000.0)
(-1,465)
kWh
- - - - $74,031
-
lb
- -
04 2.3212: Optimize plant power factor $72,160 $93,000 - - $72,160 - - - - -
05 2.5195: Change product design to reduce energy requirements $39,290 $2,720 $23,020
697,538
kWh
$16,270
-
kW-mo/yr
- - - - - -
06 3.6112: Use filter and drying oven to reduce sludge volume $25,103 $30,600 $(-6,930.0)
(-272,567)
kWh
- - - $32,033
-
gal
- - -
07 3.4155: Meter waste water $13,500 $3,700 - - - $13,500
-
Tgal
- - - -
08 2.7261: Install timers and/or thermostats $6,500 $650 $6,500
136,284
kWh
- - - - - - -
TOTAL RECOMMENDED $496,319 $194,180 $21,590
559,790
kWh
$16,270
-
kW-mo/yr
$72,160 $13,500
-
Tgal
$32,033
-
gal
$74,031
-
lb
$175,335
-
lb
$91,400
TOTAL IMPLEMENTED $200,438 $35,600 $(-6,930.0)
(-272,567)
kWh
- - - $32,033
-
gal
- $175,335
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Gaseous Waste Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs