Assessment Year | 1999 |
---|---|
Principal Product | Truck air brake actuators |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
59,500
ft2
|
Annual Production | 2,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $234,399 | 4,444,314 |
kWh
|
$0.053 |
Electricity Demand | $92,581 | 9,899 |
kW-mo/yr
|
$9.35 |
LPG | $72,585 | 12,281 |
MMBtu
|
$5.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $170,467 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $139,642 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.611: Begin a practice of predictive / preventative maintenance | $135,000 | $32,200 | - | - | - | $(-120,000.0) | - | - | - | $255,000 | |
02 | 3.6112: Use filter and drying oven to reduce sludge volume | $15,965 | $4,260 | - | - |
$8,775
-
lb
|
- | $7,190 | - | - | - | |
03 | 3.6112: Use filter and drying oven to reduce sludge volume | $6,520 | $10,300 |
$(-65.0)
(-3,224)
kWh
|
$6,585
-
gal
|
- | - | - | - | - | - | |
04 | 4.214: Purchase appropriately sized material | $5,860 | - | - | - | - | - | - | $5,860 | - | - | |
05 | 2.2437: Recover waste heat from equipment | $4,642 | $1,860 |
$4,642
145,076
kWh
|
- | - | - | - | - | - | - | |
06 | 2.7144: Install spectral reflectors / delamp | $1,890 | $3,060 |
$1,780
55,686
kWh
|
- | - | - | - | - | $110 | - | |
07 | 2.2511: Insulate bare equipment | $590 | $131 |
$590
18,464
kWh
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $170,467 | $51,811 |
$6,947
216,002
kWh
|
$6,585
-
gal
|
$8,775
-
lb
|
$(-120,000.0) | $7,190 | $5,860 | $110 | $255,000 | ||
TOTAL IMPLEMENTED | $139,642 | $34,060 |
$4,642
145,076
kWh
|
- | - | $(-120,000.0) | - | - | - | $255,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs