Assessment Year | 1998 |
---|---|
Principal Product | steel wire |
NAICS |
n/a
|
SIC | 3315: Steel Wiredrawing and Steel Nails and Spikes |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
156,000
ft2
|
Annual Production | 100,000,000
lb
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $241,113 | 9,033,119 |
kWh
|
$0.027 |
Electricity Demand | $189,243 | 20,310 |
kW-mo/yr
|
$9.32 |
Electricity Fees | $12,919 | - |
|
- |
Natural Gas | $55,941 | 9,560 |
MMBtu
|
$5.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $310,829 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $243,771 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $489 | $852 |
$157
5,862
kWh
|
$332
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.2511: Insulate bare equipment | $4,227 | $1,090 | - | - |
$4,227
-
MMBtu
|
- | - | - | |
03 | 2.2514: Cover open tanks | $5,237 | $10,500 | - | - |
$5,237
-
MMBtu
|
- | - | - | |
04 | 2.4131: Size electric motors for peak operating efficiency | $7,006 | $6,000 |
$4,406
165,006
kWh
|
$2,600
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.8113: Purchase gas directly from a contract gas supplier | $1,555 | $200 | - | - |
$1,555
-
MMBtu
|
- | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,915 | $1,448 |
$1,291
48,359
kWh
|
$624
-
kW-mo/yr
|
- | - | - | - | |
07 | 3.5313: Increase amount of waste recovered for resale | $5,400 | $200 | - | - | - |
$8,100
-
lb
|
$(-2,700.0) | - | |
08 | 4.113: Install refrigeration system to cool product | $47,500 | $135,000 | - | - | - | - | - | $47,500 | |
09 | 4.451: Add additional production shift | $237,500 | $12,000 | - | - | - | - | - | $237,500 | |
TOTAL RECOMMENDED | $310,829 | $167,290 |
$5,854
219,227
kWh
|
$3,556
-
kW-mo/yr
|
$11,019
-
MMBtu
|
$8,100
-
lb
|
$(-2,700.0) | $285,000 | ||
TOTAL IMPLEMENTED | $243,771 | $14,142 |
$157
5,862
kWh
|
$332
-
kW-mo/yr
|
$5,782
-
MMBtu
|
- | - | $237,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs