| Assessment Year | 2003 |
|---|---|
| Principal Product | Cowhide split and top-grade leather |
| NAICS | 316110: Leather and Hide Tanning and Finishing |
| SIC | 3111: Leather Tanning and Finishing |
| Sales Range | $5 M to 10M |
| # of Employees | 44 |
| Plant Area |
60,000
ft2
|
| Annual Production | 49,000
thousand feet
|
| Production Hrs. Annual | 2,328
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $98,262 | 1,194,327 |
kWh
|
$0.082 |
| Electricity Demand | $52,025 | 4,592 |
kW-mo/yr
|
$11.33 |
| Electricity Fees | $5,810 | - |
|
- |
| LPG | $22,184 | 2,116 |
MMBtu
|
$10.48 |
| Fuel Oil #4 | $48,517 | 10,296 |
MMBtu
|
$4.71 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $63,156 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.114: Add/modify equipment to improve drying process | $31,336 | $37,543 | n/a | - | - | - | $31,336 |
| 02 | 4.652: Replace existing equipment with more suitable substitutes | $21,438 | $43,874 | n/a | - | - | - | $21,438 |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,738 | $6,375 | n/a |
$3,339
40,723
kWh
|
$1,399
-
kW-mo/yr
|
- | - |
| 04 | 2.3212: Optimize plant power factor | $2,667 | $4,205 | n/a | - |
$2,667
-
kW-mo/yr
|
- | - |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,532 | $6,800 | n/a |
$1,786
21,790
kWh
|
$746
-
kW-mo/yr
|
- | - |
| 06 | 2.2136: Install / repair insulation on steam lines | $445 | $383 | n/a | - | - |
$445
-
MMBtu
|
- |
| TOTAL RECOMMENDED | $63,156 | $99,180 |
$5,125
62,513
kWh
|
$4,812
-
kW-mo/yr
|
$445
-
MMBtu
|
$52,774 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs