| Assessment Year | 1999 |
|---|---|
| Principal Product | Laminated boards, laminate sheets, fiberglass sheets |
| NAICS |
n/a
|
| SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
175,000
ft2
|
| Annual Production | 39,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $202,430 | 5,890,387 |
kWh
|
$0.034 |
| Electricity Demand | $159,641 | 18,516 |
kW-mo/yr
|
$8.62 |
| Electricity Fees | $10,364 | - |
|
- |
| Natural Gas | $160,608 | 31,620 |
MMBtu
|
$5.08 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $467,760 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $28,790 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.6123: Burn wood by-products for heat | $194,600 | $52,000 | - | - |
$74,600
-
MMBtu
|
$120,000
-
lb
|
- | |
| 02 | 3.5311: Recover and reuse waste material | $120,000 | $2,400 | - | - | - |
$120,000
-
lb
|
- | |
| 03 | 3.5316: Contract a wood pallet recycling company | $112,500 | $32,000 | - | - | - |
$112,500
-
lb
|
- | |
| 04 | 4.431: Train operators for maximum operating efficiency | $25,000 | $5,500 | - | - | - | - | $25,000 | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $9,160 | $1,400 |
$4,920
153,869
kWh
|
$4,240
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $2,780 | $2,630 |
$2,780
86,753
kWh
|
- | - | - | - | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,360 | $1,330 |
$670
20,809
kWh
|
$690
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,010 | $4,000 |
$665
20,809
kWh
|
$345
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.2437: Recover waste heat from equipment | $700 | $810 | - | - |
$700
-
MMBtu
|
- | - | |
| 10 | 2.4314: Use synthetic lubricant | $650 | - |
$310
9,672
kWh
|
$340
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $467,760 | $102,070 |
$9,345
291,912
kWh
|
$5,615
-
kW-mo/yr
|
$75,300
-
MMBtu
|
$352,500
-
lb
|
$25,000 | ||
| TOTAL IMPLEMENTED | $28,790 | $12,130 |
$3,445
107,562
kWh
|
$345
-
kW-mo/yr
|
- | - | $25,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs