Assessment Year | 1999 |
---|---|
Principal Product | Rayon staple fiber |
NAICS |
n/a
|
SIC | 2923: |
Sales Range | $50 M to 100M |
# of Employees | 410 |
Plant Area |
1,000,000
ft2
|
Annual Production | 115,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $200,299 | 7,789,566 |
kWh
|
$0.026 |
Electricity Demand | $104,651 | 10,924 |
kW-mo/yr
|
$9.58 |
Electricity Fees | $(-17,475.0) | - |
|
- |
Coal | $5,840,640 | 4,563,000 |
MMBtu
|
$1.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $874,150 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $327,320 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Coal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.4111: Use closed cycle process to minimize waste water production | $400,000 | $618,000 | - | - | - | - |
$400,000
-
Tgal
|
|
02 | 2.1212: Operate boilers on high fire setting | $175,220 | $82,400 |
$175,220
-
MMBtu
|
- | - | - | - | |
03 | 3.4151: Minimize water usage | $143,010 | $60,900 |
$48,400
-
MMBtu
|
- | - | - |
$94,610
-
Tgal
|
|
04 | 4.443: Install automatic boiler fuel feed system | $130,100 | $137,500 | - | - | $(-52,420.0) | $182,520 | - | |
05 | 3.5313: Increase amount of waste recovered for resale | $22,000 | - | - |
$22,000
-
lb
|
- | - | - | |
06 | 2.2511: Insulate bare equipment | $2,020 | $3,560 |
$2,020
-
MMBtu
|
- | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,800 | $2,380 |
$1,800
-
MMBtu
|
- | - | - | - | |
TOTAL RECOMMENDED | $874,150 | $904,740 |
$227,440
-
MMBtu
|
$22,000
-
lb
|
$(-52,420.0) | $182,520 |
$494,610
-
Tgal
|
||
TOTAL IMPLEMENTED | $327,320 | $219,900 |
$175,220
-
MMBtu
|
$22,000
-
lb
|
$(-52,420.0) | $182,520 | - | ||
Yearly Savings* | Imp'd Cost* | Coal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs