ITAC Assessment: TN0652
ITAC logo
ITAC Assessment: TN0652
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Wooden bedroom furniture
NAICS
n/a
SIC 2511: Wood Household Furniture, Except Upholstered
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 450,000
ft2
Annual Production 300,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $459,311 10,006,448
kWh
Electricity Demand $131,127 24,578
kW-mo/yr
Electricity Fees $18,891 -
Wood $400,000 104,000
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $418,090 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $241,950

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
01 3.1191: Change procedures / equipment / operating conditions $189,625 $28,000 - - - $460
-
lb
$565 $(-2,400.0) $191,000 - -
02 2.6242: Minimize operation of equipment maintained in standby condition $34,710 $27,240 $34,710
738,570
kWh
- - - - - - - -
03 3.5311: Recover and reuse waste material $23,000 $60,500 - - - $3,000
-
lb
- - - $20,000 -
04 4.421: Modify current incentive program $18,000 $49,200 - - - - $300,000 $(-540,000.0) - - $258,000
05 4.322: Eliminate old stock and modify inventory control $5,625 $16,000 - - - - - $5,625 - - -
06 2.2135: Repair and eliminate steam leaks $4,000 $100 - - $4,000
-
MMBtu
- - - - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,700 $4,000 $1,350
28,722
kWh
$350
-
kW-mo/yr
- - - - - - -
08 2.7243: Improve air circulation with destratification fans / other methods $96,250 $400,000 - - $96,250
-
MMBtu
- - - - - -
09 2.2135: Repair and eliminate steam leaks $28,970 $300 - - $28,970
-
MMBtu
- - - - - -
10 2.1223: Install smaller boiler (increase high fire duty cycle) $16,210 $10,000 - - $16,210
-
MMBtu
- - - - - -
TOTAL RECOMMENDED $418,090 $595,340 $36,060
767,292
kWh
$350
-
kW-mo/yr
$145,430
-
MMBtu
$3,460
-
lb
$300,565 $(-536,775.0) $191,000 $20,000 $258,000
TOTAL IMPLEMENTED $241,950 $157,800 $1,350
28,722
kWh
$350
-
kW-mo/yr
$4,000
-
MMBtu
$3,460
-
lb
$300,565 $(-536,775.0) $191,000 $20,000 $258,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Wood Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs