Assessment Year | 2000 |
---|---|
Principal Product | Wooden bedroom furniture |
NAICS |
n/a
|
SIC | 2511: Wood Household Furniture, Except Upholstered |
Sales Range | $10 M to 50M |
# of Employees | 400 |
Plant Area |
450,000
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $459,311 | 10,006,448 |
kWh
|
$0.046 |
Electricity Demand | $131,127 | 24,578 |
kW-mo/yr
|
$5.34 |
Electricity Fees | $18,891 | - |
|
- |
Wood | $400,000 | 104,000 |
MMBtu
|
$3.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $418,090 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $241,950 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $189,625 | $28,000 | - | - | - |
$460
-
lb
|
$565 | $(-2,400.0) | $191,000 | - | - | |
02 | 2.6242: Minimize operation of equipment maintained in standby condition | $34,710 | $27,240 |
$34,710
738,570
kWh
|
- | - | - | - | - | - | - | - | |
03 | 3.5311: Recover and reuse waste material | $23,000 | $60,500 | - | - | - |
$3,000
-
lb
|
- | - | - | $20,000 | - | |
04 | 4.421: Modify current incentive program | $18,000 | $49,200 | - | - | - | - | $300,000 | $(-540,000.0) | - | - | $258,000 | |
05 | 4.322: Eliminate old stock and modify inventory control | $5,625 | $16,000 | - | - | - | - | - | $5,625 | - | - | - | |
06 | 2.2135: Repair and eliminate steam leaks | $4,000 | $100 | - | - |
$4,000
-
MMBtu
|
- | - | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,700 | $4,000 |
$1,350
28,722
kWh
|
$350
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
08 | 2.7243: Improve air circulation with destratification fans / other methods | $96,250 | $400,000 | - | - |
$96,250
-
MMBtu
|
- | - | - | - | - | - | |
09 | 2.2135: Repair and eliminate steam leaks | $28,970 | $300 | - | - |
$28,970
-
MMBtu
|
- | - | - | - | - | - | |
10 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $16,210 | $10,000 | - | - |
$16,210
-
MMBtu
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $418,090 | $595,340 |
$36,060
767,292
kWh
|
$350
-
kW-mo/yr
|
$145,430
-
MMBtu
|
$3,460
-
lb
|
$300,565 | $(-536,775.0) | $191,000 | $20,000 | $258,000 | ||
TOTAL IMPLEMENTED | $241,950 | $157,800 |
$1,350
28,722
kWh
|
$350
-
kW-mo/yr
|
$4,000
-
MMBtu
|
$3,460
-
lb
|
$300,565 | $(-536,775.0) | $191,000 | $20,000 | $258,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs