ITAC Assessment: TN0647
ITAC logo
ITAC Assessment: TN0647
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Thermo-formed plastic components
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 42,500
ft2
Annual Production 2,500,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $113,530 3,292,204
kWh
Electricity Demand $61,900 7,263
kW-mo/yr
Electricity Fees $1,820 -
Natural Gas $9,736 1,856
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,116,135 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $530

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 3.1182: Make a new by-product $754,000 $1,851,360 - - $2,590,000
-
lb
$(-1,836,000.0)
02 3.5313: Increase amount of waste recovered for resale $339,565 $329,440 $(-7,680.0)
(-232,708)
kWh
$(-4,670.0)
-
kW-mo/yr
$376,875
-
lb
$(-24,960.0)
03 4.421: Modify current incentive program $21,000 $16,000 - - - $21,000
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,040 $500 $700
21,102
kWh
$340
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $530 - $300
9,086
kWh
$230
-
kW-mo/yr
- -
TOTAL RECOMMENDED $1,116,135 $2,197,300 $(-6,680.0)
(-202,520)
kWh
$(-4,100.0)
-
kW-mo/yr
$2,966,875
-
lb
$(-1,839,960.0)
TOTAL IMPLEMENTED $530 - $300
9,086
kWh
$230
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs