| Assessment Year | 1999 |
|---|---|
| Principal Product | Thermo-formed plastic components |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
42,500
ft2
|
| Annual Production | 2,500,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $113,530 | 3,292,204 |
kWh
|
$0.034 |
| Electricity Demand | $61,900 | 7,263 |
kW-mo/yr
|
$8.52 |
| Electricity Fees | $1,820 | - |
|
- |
| Natural Gas | $9,736 | 1,856 |
MMBtu
|
$5.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,116,135 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $530 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.1182: Make a new by-product | $754,000 | $1,851,360 | - | - |
$2,590,000
-
lb
|
$(-1,836,000.0) | |
| 02 | 3.5313: Increase amount of waste recovered for resale | $339,565 | $329,440 |
$(-7,680.0)
(-232,708)
kWh
|
$(-4,670.0)
-
kW-mo/yr
|
$376,875
-
lb
|
$(-24,960.0) | |
| 03 | 4.421: Modify current incentive program | $21,000 | $16,000 | - | - | - | $21,000 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,040 | $500 |
$700
21,102
kWh
|
$340
-
kW-mo/yr
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $530 | - |
$300
9,086
kWh
|
$230
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $1,116,135 | $2,197,300 |
$(-6,680.0)
(-202,520)
kWh
|
$(-4,100.0)
-
kW-mo/yr
|
$2,966,875
-
lb
|
$(-1,839,960.0) | ||
| TOTAL IMPLEMENTED | $530 | - |
$300
9,086
kWh
|
$230
-
kW-mo/yr
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs