Assessment Year | 1998 |
---|---|
Principal Product | High density polyethylene conduit and water pipe |
NAICS |
n/a
|
SIC | 3084: Plastics Pipe |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
112,500
ft2
|
Annual Production | 30,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $270,435 | 9,299,531 |
kWh
|
$0.029 |
Electricity Demand | $66,127 | 15,710 |
kW-mo/yr
|
$4.21 |
Electricity Fees | $73,851 | - |
|
- |
Natural Gas | $10,756 | 1,329 |
MMBtu
|
$8.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $439,485 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $53,400 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.5215: Avoid contamination of end pieces and reuse as feed stock | $363,750 | $20,000 | - | - | - | - | $(-30,000.0) | $393,750 | |
02 | 3.1191: Change procedures / equipment / operating conditions | $32,370 | $50,000 | - | - | - | $(-20,000.0) | - | $52,370 | |
03 | 4.611: Begin a practice of predictive / preventative maintenance | $17,850 | $32,200 | - | - | - | - | - | $17,850 | |
04 | 2.3212: Optimize plant power factor | $11,910 | $1,440 | - | - | $11,910 | - | - | - | |
05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $7,575 | $8,575 |
$6,880
275,205
kWh
|
$695
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,180 | $2,030 |
$2,020
80,891
kWh
|
$1,160
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.2511: Insulate bare equipment | $2,850 | $1,100 |
$2,290
91,735
kWh
|
$560
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $439,485 | $115,345 |
$11,190
447,831
kWh
|
$2,415
-
kW-mo/yr
|
$11,910 | $(-20,000.0) | $(-30,000.0) | $463,970 | ||
TOTAL IMPLEMENTED | $53,400 | $84,230 |
$2,020
80,891
kWh
|
$1,160
-
kW-mo/yr
|
- | $(-20,000.0) | - | $70,220 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs