ITAC Assessment: OK0068
ITAC logo
ITAC Assessment: OK0068
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product SOFT DRINKS
NAICS
n/a
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $1
M
to 5
M
# of Employees 70
Plant Area
n/a
Annual Production 1,000,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $123,257 3,005,862
kWh
Natural Gas $60,029 19,964
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,728 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $1,110 $695 - $1,110
-
MMBtu
02 3.4154: Eliminate leaks in water lines and valves $508 $295 - $508
-
MMBtu
03 2.7261: Install timers and/or thermostats $243 $485 - $243
-
MMBtu
04 2.7261: Install timers and/or thermostats $132 $485 $132
3,810
kWh
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $342 $50 $342
9,965
kWh
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $11,393 $35,880 $11,393
324,443
kWh
-
TOTAL RECOMMENDED $13,728 $37,890 $11,867
338,218
kWh
$1,861
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs