| Assessment Year | 1998 |
|---|---|
| Principal Product | Bonded urethane carpet pad |
| NAICS |
n/a
|
| SIC | 3086: Plastics Foam Products |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
107,000
ft2
|
| Annual Production | 8,600
ton
|
| Production Hrs. Annual | 6,006
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $94,781 | 2,814,771 |
kWh
|
$0.034 |
| Electricity Demand | $79,589 | 9,210 |
kW-mo/yr
|
$8.64 |
| Electricity Fees | $2,752 | - |
|
- |
| Natural Gas | $83,715 | 15,806 |
MMBtu
|
$5.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $171,950 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $169,840 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.423: Move product using mechanical means | $135,200 | $72,120 | - | - | - | - | $135,200 | - | |
| 02 | 4.611: Begin a practice of predictive / preventative maintenance | $24,975 | $27,000 | - | - | - | - | - | $24,975 | |
| 03 | 3.7212: Improved material handling (mixing and transfer) | $7,440 | $400 | - | - |
$7,440
-
gal
|
- | - | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,140 | $2,765 |
$770
23,447
kWh
|
$1,370
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $2,110 | $830 |
$1,310
39,566
kWh
|
$800
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 3.5316: Contract a wood pallet recycling company | $85 | $50 | - | - | - |
$85
-
lb
|
- | - | |
| TOTAL RECOMMENDED | $171,950 | $103,165 |
$2,080
63,013
kWh
|
$2,170
-
kW-mo/yr
|
$7,440
-
gal
|
$85
-
lb
|
$135,200 | $24,975 | ||
| TOTAL IMPLEMENTED | $169,840 | $102,335 |
$770
23,447
kWh
|
$1,370
-
kW-mo/yr
|
$7,440
-
gal
|
$85
-
lb
|
$135,200 | $24,975 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs