Assessment Year | 1998 |
---|---|
Principal Product | Bonded urethane carpet pad |
NAICS |
n/a
|
SIC | 3086: Plastics Foam Products |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
107,000
ft2
|
Annual Production | 8,600
ton
|
Production Hrs. Annual | 6,006
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $94,781 | 2,814,771 |
kWh
|
$0.034 |
Electricity Demand | $79,589 | 9,210 |
kW-mo/yr
|
$8.64 |
Electricity Fees | $2,752 | - |
|
- |
Natural Gas | $83,715 | 15,806 |
MMBtu
|
$5.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $171,950 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $169,840 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.423: Move product using mechanical means | $135,200 | $72,120 | - | - | - | - | $135,200 | - | |
02 | 4.611: Begin a practice of predictive / preventative maintenance | $24,975 | $27,000 | - | - | - | - | - | $24,975 | |
03 | 3.7212: Improved material handling (mixing and transfer) | $7,440 | $400 | - | - |
$7,440
-
gal
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,140 | $2,765 |
$770
23,447
kWh
|
$1,370
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $2,110 | $830 |
$1,310
39,566
kWh
|
$800
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.5316: Contract a wood pallet recycling company | $85 | $50 | - | - | - |
$85
-
lb
|
- | - | |
TOTAL RECOMMENDED | $171,950 | $103,165 |
$2,080
63,013
kWh
|
$2,170
-
kW-mo/yr
|
$7,440
-
gal
|
$85
-
lb
|
$135,200 | $24,975 | ||
TOTAL IMPLEMENTED | $169,840 | $102,335 |
$770
23,447
kWh
|
$1,370
-
kW-mo/yr
|
$7,440
-
gal
|
$85
-
lb
|
$135,200 | $24,975 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs