| Assessment Year | 1998 |
|---|---|
| Principal Product | Hydraulic cylinders |
| NAICS |
n/a
|
| SIC | 3593: Fluid Power Cylinders and Actuators |
| Sales Range | $10 M to 50M |
| # of Employees | 126 |
| Plant Area |
62,000
ft2
|
| Annual Production | 17,200
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $29,804 | 1,414,127 |
kWh
|
$0.021 |
| Electricity Demand | $31,254 | 3,624 |
kW-mo/yr
|
$8.62 |
| Electricity Fees | $1,466 | - |
|
- |
| Natural Gas | $14,691 | 2,256 |
MMBtu
|
$6.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,420 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $995 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.514: Re-arrange equipment layout to reduce handling costs | $46,480 | $37,380 | - | - | $46,480 | |
| 02 | 3.6192: Use a less expensive method of waste removal | $1,455 | - | - |
$1,455
-
lb
|
- | |
| 03 | 2.2511: Insulate bare equipment | $670 | $220 |
$670
29,894
kWh
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $490 | $980 |
$490
21,981
kWh
|
- | - | |
| 05 | 3.6192: Use a less expensive method of waste removal | $175 | - | - |
$175
-
lb
|
- | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $150 | $600 |
$150
6,448
kWh
|
- | - | |
| TOTAL RECOMMENDED | $49,420 | $39,180 |
$1,310
58,323
kWh
|
$1,630
-
lb
|
$46,480 | ||
| TOTAL IMPLEMENTED | $995 | $820 |
$820
36,342
kWh
|
$175
-
lb
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs