Assessment Year | 1998 |
---|---|
Principal Product | Wood and upholstered household furniture |
NAICS |
n/a
|
SIC | 2512: Wood Household Furniture, Upholstered |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
180,000
ft2
|
Annual Production | 5,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,793 | 1,487,691 |
kWh
|
$0.042 |
Electricity Demand | $53,718 | 7,440 |
kW-mo/yr
|
$7.22 |
Electricity Fees | $3,677 | - |
|
- |
Natural Gas | $61,245 | 9,582 |
MMBtu
|
$6.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $171,658 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $161,868 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.431: Train operators for maximum operating efficiency | $84,680 | $200,000 | - | - | - | - | $(-64,900.0) | $(-30,420.0) | - | $180,000 | |
02 | 3.1191: Change procedures / equipment / operating conditions | $67,500 | $50,000 | - | - | - |
$(-67,500.0)
-
lb
|
- | - | $135,000 | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $5,720 | $2,600 |
$2,860
67,995
kWh
|
$2,860
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 3.5313: Increase amount of waste recovered for resale | $3,600 | - | - | - | - |
$3,600
-
lb
|
- | - | - | - | |
05 | 2.6242: Minimize operation of equipment maintained in standby condition | $2,990 | $8,575 |
$2,990
71,219
kWh
|
- | - | - | - | - | - | - | |
06 | 2.7261: Install timers and/or thermostats | $1,990 | $510 |
$1,990
47,479
kWh
|
- | - | - | - | - | - | - | |
07 | 2.2163: Use minimum steam operating pressure | $1,460 | - | - | - |
$1,460
-
MMBtu
|
- | - | - | - | - | |
08 | 2.7229: Air condition only space necessary | $1,310 | - | - | - |
$1,310
-
MMBtu
|
- | - | - | - | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,038 | $1,820 |
$345
8,206
kWh
|
$693
-
kW-mo/yr
|
- | - | - | - | - | - | |
10 | 2.2511: Insulate bare equipment | $430 | $390 | - | - |
$430
-
MMBtu
|
- | - | - | - | - | |
11 | 2.2437: Recover waste heat from equipment | $320 | $960 | - | - |
$320
-
MMBtu
|
- | - | - | - | - | |
12 | 2.2135: Repair and eliminate steam leaks | $310 | $295 | - | - |
$310
-
MMBtu
|
- | - | - | - | - | |
13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $310 | $500 |
$135
3,224
kWh
|
$175
-
kW-mo/yr
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $171,658 | $265,650 |
$8,320
198,123
kWh
|
$3,728
-
kW-mo/yr
|
$3,830
-
MMBtu
|
$(-63,900.0)
-
lb
|
$(-64,900.0) | $(-30,420.0) | $135,000 | $180,000 | ||
TOTAL IMPLEMENTED | $161,868 | $256,685 |
$5,330
126,904
kWh
|
$3,728
-
kW-mo/yr
|
$630
-
MMBtu
|
$(-67,500.0)
-
lb
|
$(-64,900.0) | $(-30,420.0) | $135,000 | $180,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs