ITAC Assessment: TN0634
ITAC logo
ITAC Assessment: TN0634
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Wood and upholstered household furniture
NAICS
n/a
SIC 2512: Wood Household Furniture, Upholstered
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 180,000
ft2
Annual Production 5,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,793 1,487,691
kWh
Electricity Demand $53,718 7,440
kW-mo/yr
Electricity Fees $3,677 -
Natural Gas $61,245 9,582
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $171,658 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $161,868

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings
01 4.431: Train operators for maximum operating efficiency $84,680 $200,000 - - - - $(-64,900.0) $(-30,420.0) - $180,000
02 3.1191: Change procedures / equipment / operating conditions $67,500 $50,000 - - - $(-67,500.0)
-
lb
- - $135,000 -
03 2.7111: Reduce illumination to minimum necessary levels $5,720 $2,600 $2,860
67,995
kWh
$2,860
-
kW-mo/yr
- - - - - -
04 3.5313: Increase amount of waste recovered for resale $3,600 - - - - $3,600
-
lb
- - - -
05 2.6242: Minimize operation of equipment maintained in standby condition $2,990 $8,575 $2,990
71,219
kWh
- - - - - - -
06 2.7261: Install timers and/or thermostats $1,990 $510 $1,990
47,479
kWh
- - - - - - -
07 2.2163: Use minimum steam operating pressure $1,460 - - - $1,460
-
MMBtu
- - - - -
08 2.7229: Air condition only space necessary $1,310 - - - $1,310
-
MMBtu
- - - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,038 $1,820 $345
8,206
kWh
$693
-
kW-mo/yr
- - - - - -
10 2.2511: Insulate bare equipment $430 $390 - - $430
-
MMBtu
- - - - -
11 2.2437: Recover waste heat from equipment $320 $960 - - $320
-
MMBtu
- - - - -
12 2.2135: Repair and eliminate steam leaks $310 $295 - - $310
-
MMBtu
- - - - -
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $310 $500 $135
3,224
kWh
$175
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $171,658 $265,650 $8,320
198,123
kWh
$3,728
-
kW-mo/yr
$3,830
-
MMBtu
$(-63,900.0)
-
lb
$(-64,900.0) $(-30,420.0) $135,000 $180,000
TOTAL IMPLEMENTED $161,868 $256,685 $5,330
126,904
kWh
$3,728
-
kW-mo/yr
$630
-
MMBtu
$(-67,500.0)
-
lb
$(-64,900.0) $(-30,420.0) $135,000 $180,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs