Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Precision balls and rollers
NAICS
n/a
SIC 3526:
Sales Range $50
M
to 100
M
# of Employees 258
Plant Area 123,000
ft2
Annual Production 86,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $467,442 17,054,807
kWh
Electricity Demand $188,551 20,138
kW-mo/yr
Electricity Fees $27,994 -
Natural Gas $83,282 12,780
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $174,390 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $87,730

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Primary Raw Material Savings Primary Product Savings
01 3.1192: Reduce scrap production $62,560 $5,700 - - - - - $62,560 -
02 3.6112: Use filter and drying oven to reduce sludge volume $35,290 $98,000 $(-3,430.0)
(-137,163)
kWh
- - - $38,720
-
gal
- -
03 3.3128: Utilize other methods to remove contaminants $24,360 $9,800 - - - - $24,360
-
gal
- -
04 4.431: Train operators for maximum operating efficiency $21,285 $25,800 - - - - - - $21,285
05 3.4151: Minimize water usage $16,270 - - - - $16,270
-
Tgal
- - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $9,370 $10,185 $4,540
181,712
kWh
$4,830
-
kW-mo/yr
- - - - -
07 2.5194: Redesign process $2,675 $1,100 - - $2,675
-
MMBtu
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,370 $1,800 $880
35,170
kWh
$490
-
kW-mo/yr
- - - - -
09 3.4155: Meter waste water $1,210 $2,980 - - - $1,210
-
Tgal
- - -
TOTAL RECOMMENDED $174,390 $155,365 $1,990
79,719
kWh
$5,320
-
kW-mo/yr
$2,675
-
MMBtu
$17,480
-
Tgal
$63,080
-
gal
$62,560 $21,285
TOTAL IMPLEMENTED $87,730 $35,580 - - $2,675
-
MMBtu
$1,210
-
Tgal
- $62,560 $21,285
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Primary Raw Material Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs