Assessment Year | 2019 |
---|---|
Principal Product | Bacon Bits |
NAICS | 311611: Animal (except Poultry) Slaughtering |
SIC | 2011: Meat Packing Plants |
Sales Range | $50 M to 100M |
# of Employees | 137 |
Plant Area |
45,000
ft2
|
Annual Production | 23,000,000
units
|
Production Hrs. Annual | 7,900
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $214,968 | 4,378,200 |
kWh
|
$0.049 | |
Electricity Demand | $155,229 | 9,758 |
kW-mo/yr
|
$15.91 | |
Electricity Fees | $275 | - |
|
- | |
Natural Gas | $132,325 | 30,970 |
MMBtu
|
$4.27 | |
Waste Disposal Costs | |||||
Water Usage | $23,408 | 13,926 |
Tgal
|
$1.68 | |
Water Disposal | $16,037 | 13,747 |
Tgal
|
$1.17 | |
TOTAL YEARLY COSTS | $542,243 | ||||
RECOMMENDED SAVINGS* | $87,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $87,390 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $36,367 | $39,000 | - | - | $36,367 | - | - | - | - | - | |
02 | 2.2113: Repair or replace steam traps | $15,324 | $44 | - | - | - |
$16,380
-
MMBtu
|
- | - | $(-1,056.0) | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,128 | $2,497 |
$8,644
176,415
kWh
|
$5,483
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 3.4151: Minimize water usage | $10,832 | $1,127 | - | - | - |
$3,059
-
MMBtu
|
$4,589
-
Tgal
|
$3,183
-
Tgal
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,739 | $1,600 |
$11,191
228,393
kWh
|
- | - | - | - | - | $(-352.0) | $(-100.0) | |
TOTAL RECOMMENDED | $87,390 | $44,268 |
$19,835
404,808
kWh
|
$5,483
-
kW-mo/yr
|
$36,367 |
$19,439
-
MMBtu
|
$4,589
-
Tgal
|
$3,183
-
Tgal
|
$(-1,408.0) | $(-100.0) | ||
TOTAL IMPLEMENTED | $87,390 | $44,268 |
$19,835
404,808
kWh
|
$5,483
-
kW-mo/yr
|
$36,367 |
$19,439
-
MMBtu
|
$4,589
-
Tgal
|
$3,183
-
Tgal
|
$(-1,408.0) | $(-100.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs