Assessment Year | 1998 |
---|---|
Principal Product | Animal feed |
NAICS |
n/a
|
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
110,000
ft2
|
Annual Production | 325,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $140,002 | 4,467,761 |
kWh
|
$0.031 |
Electricity Demand | $126,184 | 15,803 |
kW-mo/yr
|
$7.98 |
Electricity Fees | $2,047 | - |
|
- |
Natural Gas | $76,070 | 17,721 |
MMBtu
|
$4.29 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $160,886 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,395 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.445: Install equipment to move product | $147,240 | $377,000 |
$(-15,000.0)
(-498,242)
kWh
|
- | - | $162,240 | - | - | |
02 | 3.5311: Recover and reuse waste material | $6,480 | $500 | - | - |
$3,480
-
lb
|
- | - | $3,000 | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,860 | $4,550 |
$970
32,239
kWh
|
$1,890
-
kW-mo/yr
|
- | - | - | - | |
04 | 3.6192: Use a less expensive method of waste removal | $2,535 | - | - | - |
$7,410
-
lb
|
- | $(-4,875.0) | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,390 | - |
$790
26,377
kWh
|
$600
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.5217: Reuse / recycle/ sell paper products | $381 | $600 | - | - |
$381
-
lb
|
- | - | - | |
TOTAL RECOMMENDED | $160,886 | $382,650 |
$(-13,240.0)
(-439,626)
kWh
|
$2,490
-
kW-mo/yr
|
$11,271
-
lb
|
$162,240 | $(-4,875.0) | $3,000 | ||
TOTAL IMPLEMENTED | $5,395 | $4,550 |
$970
32,239
kWh
|
$1,890
-
kW-mo/yr
|
$7,410
-
lb
|
- | $(-4,875.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs