Assessment Year | 1998 |
---|---|
Principal Product | Commercial printed material |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
67,000
ft2
|
Annual Production | 234,000,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $58,523 | 2,432,884 |
kWh
|
$0.024 |
Electricity Demand | $54,646 | 5,873 |
kW-mo/yr
|
$9.30 |
Electricity Fees | $408 | - |
|
- |
Natural Gas | $31,244 | 4,992 |
MMBtu
|
$6.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $112,115 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $745 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1192: Reduce scrap production | $54,000 | $34,400 | - | - | - | - | $54,000 | - | |
02 | 4.624: Hire additional personnel to reduce changeout time | $28,700 | $17,200 |
$(-550.0)
(-23,154)
kWh
|
- | - | - | - | $29,250 | |
03 | 4.421: Modify current incentive program | $25,000 | $10,000 | - | - | - | $(-10,000.0) | - | $35,000 | |
04 | 2.7261: Install timers and/or thermostats | $2,750 | $780 |
$2,750
114,596
kWh
|
- | - | - | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $745 | - | - | - |
$745
-
lb
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $580 | $225 |
$120
4,982
kWh
|
$460
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $340 | - |
$110
4,689
kWh
|
$230
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $112,115 | $62,605 |
$2,430
101,113
kWh
|
$690
-
kW-mo/yr
|
$745
-
lb
|
$(-10,000.0) | $54,000 | $64,250 | ||
TOTAL IMPLEMENTED | $745 | - | - | - |
$745
-
lb
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs