ITAC Assessment: TN0622
ITAC logo
ITAC Assessment: TN0622
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Commercial printed material
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 67,000
ft2
Annual Production 234,000,000
pieces
Production Hrs. Annual 7,488
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $58,523 2,432,884
kWh
Electricity Demand $54,646 5,873
kW-mo/yr
Electricity Fees $408 -
Natural Gas $31,244 4,992
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $112,115 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $745

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 3.1192: Reduce scrap production $54,000 $34,400 - - - - $54,000 -
02 4.624: Hire additional personnel to reduce changeout time $28,700 $17,200 $(-550.0)
(-23,154)
kWh
- - - - $29,250
03 4.421: Modify current incentive program $25,000 $10,000 - - - $(-10,000.0) - $35,000
04 2.7261: Install timers and/or thermostats $2,750 $780 $2,750
114,596
kWh
- - - - -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $745 - - - $745
-
lb
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $580 $225 $120
4,982
kWh
$460
-
kW-mo/yr
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $340 - $110
4,689
kWh
$230
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $112,115 $62,605 $2,430
101,113
kWh
$690
-
kW-mo/yr
$745
-
lb
$(-10,000.0) $54,000 $64,250
TOTAL IMPLEMENTED $745 - - - $745
-
lb
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs