ITAC Assessment: TN0615
ITAC logo
ITAC Assessment: TN0615
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Dry chemical, CO2 and Haletron fire extinguishers
NAICS
n/a
SIC 3999: Manufacturing Industries, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 100,000
ft2
Annual Production 300,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $127,882 3,027,550
kWh
Electricity Demand $55,799 11,248
kW-mo/yr
Electricity Fees $6,957 -
Natural Gas $101,704 18,049
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $108,565 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,100

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
01 4.423: Move product using mechanical means $24,785 $73,860 $(-565.0)
(-13,775)
kWh
$(-130.0)
-
kW-mo/yr
- - $25,480 - - - -
02 4.421: Modify current incentive program $27,000 $10,000 - - - - $42,000 $(-15,000.0) - - -
03 2.7231: Use radiant heater for spot heating $16,845 $13,160 - - $16,845
-
MMBtu
- - - - - -
04 3.7212: Improved material handling (mixing and transfer) $17,115 $12,040 - - - $2,250
-
lb
$2,365 - $12,500 - -
05 2.3134: Shift from daytime to nighttime operation $8,850 $13,650 - $22,500
-
kW-mo/yr
- - - - - - $(-13,650.0)
06 3.1223: Use fog nozzles / spray rinsing instead of immersion rinsing $6,995 $16,930 - - - $3,250
-
lb
- - - $3,745 -
07 2.2514: Cover open tanks $5,350 $300 $5,350
280,188
kWh
- - - - - - - -
08 2.2437: Recover waste heat from equipment $830 $2,525 $830
43,376
kWh
- - - - - - - -
09 3.3128: Utilize other methods to remove contaminants $540 $1,490 - - - - - - - $540 -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $255 $280 $60
1,465
kWh
$195
-
kW-mo/yr
- - - - - - -
TOTAL RECOMMENDED $108,565 $144,235 $5,675
311,254
kWh
$22,565
-
kW-mo/yr
$16,845
-
MMBtu
$5,500
-
lb
$69,845 $(-15,000.0) $12,500 $4,285 $(-13,650.0)
TOTAL IMPLEMENTED $17,100 $13,440 $60
1,465
kWh
$195
-
kW-mo/yr
$16,845
-
MMBtu
- - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs