Assessment Year | 1997 |
---|---|
Principal Product | Dry chemical, CO2 and Haletron fire extinguishers |
NAICS |
n/a
|
SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
100,000
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $127,882 | 3,027,550 |
kWh
|
$0.042 |
Electricity Demand | $55,799 | 11,248 |
kW-mo/yr
|
$4.96 |
Electricity Fees | $6,957 | - |
|
- |
Natural Gas | $101,704 | 18,049 |
MMBtu
|
$5.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $108,565 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,100 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.423: Move product using mechanical means | $24,785 | $73,860 |
$(-565.0)
(-13,775)
kWh
|
$(-130.0)
-
kW-mo/yr
|
- | - | $25,480 | - | - | - | - | |
02 | 4.421: Modify current incentive program | $27,000 | $10,000 | - | - | - | - | $42,000 | $(-15,000.0) | - | - | - | |
03 | 2.7231: Use radiant heater for spot heating | $16,845 | $13,160 | - | - |
$16,845
-
MMBtu
|
- | - | - | - | - | - | |
04 | 3.7212: Improved material handling (mixing and transfer) | $17,115 | $12,040 | - | - | - |
$2,250
-
lb
|
$2,365 | - | $12,500 | - | - | |
05 | 2.3134: Shift from daytime to nighttime operation | $8,850 | $13,650 | - |
$22,500
-
kW-mo/yr
|
- | - | - | - | - | - | $(-13,650.0) | |
06 | 3.1223: Use fog nozzles / spray rinsing instead of immersion rinsing | $6,995 | $16,930 | - | - | - |
$3,250
-
lb
|
- | - | - | $3,745 | - | |
07 | 2.2514: Cover open tanks | $5,350 | $300 |
$5,350
280,188
kWh
|
- | - | - | - | - | - | - | - | |
08 | 2.2437: Recover waste heat from equipment | $830 | $2,525 |
$830
43,376
kWh
|
- | - | - | - | - | - | - | - | |
09 | 3.3128: Utilize other methods to remove contaminants | $540 | $1,490 | - | - | - | - | - | - | - | $540 | - | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $255 | $280 |
$60
1,465
kWh
|
$195
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $108,565 | $144,235 |
$5,675
311,254
kWh
|
$22,565
-
kW-mo/yr
|
$16,845
-
MMBtu
|
$5,500
-
lb
|
$69,845 | $(-15,000.0) | $12,500 | $4,285 | $(-13,650.0) | ||
TOTAL IMPLEMENTED | $17,100 | $13,440 |
$60
1,465
kWh
|
$195
-
kW-mo/yr
|
$16,845
-
MMBtu
|
- | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs