| Assessment Year | 1997 |
|---|---|
| Principal Product | Custom Houseboats |
| NAICS |
n/a
|
| SIC | 3732: Boat Building and Repairing |
| Sales Range | $10 M to 50M |
| # of Employees | 162 |
| Plant Area |
211,500
ft2
|
| Annual Production | 150
pieces
|
| Production Hrs. Annual | 2,625
hrs
|
| Location (State) | Kentucky |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $34,459 | 1,025,498 |
kWh
|
$0.034 |
| Electricity Demand | $22,486 | 3,748 |
kW-mo/yr
|
$6.00 |
| Electricity Fees | $2,086 | - |
|
- |
| Natural Gas | $37,715 | 9,637 |
MMBtu
|
$3.91 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $248,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $238,335 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.111: Add equipment/ operators to reduce production bottleneck | $201,410 | $28,000 |
$(-9,820.0)
(-288,980)
kWh
|
- |
$(-1,740.0)
-
MMBtu
|
- | - | $(-544,530.0) | - | $757,500 | |
| 02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $34,735 | $41,885 |
$(-1,265.0)
(-37,222)
kWh
|
- | - | - |
$42,000
-
lb
|
$(-6,000.0) | - | - | |
| 03 | 3.8142: Distill contaminated solvents for reuse | $9,975 | $9,596 |
$(-150.0)
(-4,396)
kWh
|
- | - |
$3,150
-
gal
|
- | $4,320 | $2,655 | - | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $1,330 | $3,240 | - | - |
$1,330
-
MMBtu
|
- | - | - | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $860 | - |
$360
10,551
kWh
|
$500
-
kW-mo/yr
|
- | - | - | - | - | - | |
| TOTAL RECOMMENDED | $248,310 | $82,721 |
$(-10,875.0)
(-320,047)
kWh
|
$500
-
kW-mo/yr
|
$(-410.0)
-
MMBtu
|
$3,150
-
gal
|
$42,000
-
lb
|
$(-546,210.0) | $2,655 | $757,500 | ||
| TOTAL IMPLEMENTED | $238,335 | $73,125 |
$(-10,725.0)
(-315,651)
kWh
|
$500
-
kW-mo/yr
|
$(-410.0)
-
MMBtu
|
- |
$42,000
-
lb
|
$(-550,530.0) | - | $757,500 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs