ITAC Assessment: TN0611
ITAC logo
ITAC Assessment: TN0611
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Custom Houseboats
NAICS
n/a
SIC 3732: Boat Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 162
Plant Area 211,500
ft2
Annual Production 150
pieces
Production Hrs. Annual 2,625
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,459 1,025,498
kWh
Electricity Demand $22,486 3,748
kW-mo/yr
Electricity Fees $2,086 -
Natural Gas $37,715 9,637
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $248,310 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $238,335

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $201,410 $28,000 $(-9,820.0)
(-288,980)
kWh
- $(-1,740.0)
-
MMBtu
- - $(-544,530.0) - $757,500
02 3.6193: Install equipment (eg compactor) to reduce disposal costs $34,735 $41,885 $(-1,265.0)
(-37,222)
kWh
- - - $42,000
-
lb
$(-6,000.0) - -
03 3.8142: Distill contaminated solvents for reuse $9,975 $9,596 $(-150.0)
(-4,396)
kWh
- - $3,150
-
gal
- $4,320 $2,655 -
04 2.7232: Replace existing hvac unit with high efficiency model $1,330 $3,240 - - $1,330
-
MMBtu
- - - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $860 - $360
10,551
kWh
$500
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $248,310 $82,721 $(-10,875.0)
(-320,047)
kWh
$500
-
kW-mo/yr
$(-410.0)
-
MMBtu
$3,150
-
gal
$42,000
-
lb
$(-546,210.0) $2,655 $757,500
TOTAL IMPLEMENTED $238,335 $73,125 $(-10,725.0)
(-315,651)
kWh
$500
-
kW-mo/yr
$(-410.0)
-
MMBtu
- $42,000
-
lb
$(-550,530.0) - $757,500
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs