Assessment Year | 1996 |
---|---|
Principal Product | Frozen poultry products |
NAICS |
n/a
|
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
70,000
ft2
|
Annual Production | 75,000,000
lb
|
Production Hrs. Annual | 6,552
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $440,097 | 14,691,384 |
kWh
|
$0.030 |
Electricity Demand | $267,365 | 29,353 |
kW-mo/yr
|
$9.11 |
Natural Gas | $289,685 | 82,492 |
MMBtu
|
$3.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $269,180 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $93,770 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.5194: Redesign process | $97,310 | $38,900 |
$(-620.0)
(-20,516)
kWh
|
$(-350.0)
-
kW-mo/yr
|
- | - | $98,280 | - | |
02 | 3.4156: Use flow control valves on equipment to optimize water use | $80,150 | $1,130 | - | - | - |
$47,300
-
Tgal
|
- |
$32,850
-
Tgal
|
|
03 | 2.2437: Recover waste heat from equipment | $40,800 | $99,260 | - | - |
$40,800
-
MMBtu
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $37,300 | $61,100 |
$37,300
1,243,552
kWh
|
- | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,870 | $4,200 |
$4,300
143,611
kWh
|
$2,570
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,170 | $7,000 |
$3,370
112,251
kWh
|
$2,800
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $580 | $410 |
$110
3,810
kWh
|
$470
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $269,180 | $212,000 |
$44,460
1,482,708
kWh
|
$5,490
-
kW-mo/yr
|
$40,800
-
MMBtu
|
$47,300
-
Tgal
|
$98,280 |
$32,850
-
Tgal
|
||
TOTAL IMPLEMENTED | $93,770 | $12,740 |
$7,780
259,672
kWh
|
$5,840
-
kW-mo/yr
|
- |
$47,300
-
Tgal
|
- |
$32,850
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs