Assessment Year | 1996 |
---|---|
Principal Product | Dessert mint candy |
NAICS |
n/a
|
SIC | 2064: Candy and Other Confectionery Products |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
65,000
ft2
|
Annual Production | 7,500,000
lb
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,815 | 576,202 |
kWh
|
$0.045 |
Electricity Demand | $24,563 | 2,777 |
kW-mo/yr
|
$8.85 |
Electricity Fees | $2,073 | - |
|
- |
LPG | $52,507 | 5,609 |
MMBtu
|
$9.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $243,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $80,500 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.211: Consider use / purchase of bulk materials where possible | $115,000 | $140,000 | - | - | - |
$2,000
-
lb
|
$65,000 | $48,000 | - | |
02 | 3.1191: Change procedures / equipment / operating conditions | $79,000 | $22,000 | - | - |
$157,000
-
gal
|
- | $(-78,000.0) | - | - | |
03 | 3.1191: Change procedures / equipment / operating conditions | $36,000 | $600 | - | - |
$36,000
-
gal
|
- | - | - | - | |
04 | 2.8113: Purchase gas directly from a contract gas supplier | $7,000 | - | - | - | - | - | - | $7,000 | - | |
05 | 3.1161: Eliminate/reduce an operation | $5,000 | $9,000 | - | - | - | - | - | - | $5,000 | |
06 | 2.7124: Make a practice of turning off lights when not needed | $1,000 | - |
$1,000
14,654
kWh
|
- | - | - | - | - | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $500 | $300 | - |
$500
-
MMBtu
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $243,500 | $171,900 |
$1,000
14,654
kWh
|
$500
-
MMBtu
|
$193,000
-
gal
|
$2,000
-
lb
|
$(-13,000.0) | $55,000 | $5,000 | ||
TOTAL IMPLEMENTED | $80,500 | $22,300 |
$1,000
14,654
kWh
|
$500
-
MMBtu
|
$157,000
-
gal
|
- | $(-78,000.0) | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs