ITAC Assessment: TN0574
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Dessert mint candy
NAICS
n/a
SIC 2064: Candy and Other Confectionery Products
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 65,000
ft2
Annual Production 7,500,000
lb
Production Hrs. Annual 2,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,815 576,202
kWh
Electricity Demand $24,563 2,777
kW-mo/yr
Electricity Fees $2,073 -
LPG $52,507 5,609
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $243,500 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $80,500

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 4.211: Consider use / purchase of bulk materials where possible $115,000 $140,000 - - - $2,000
-
lb
$65,000 $48,000 -
02 3.1191: Change procedures / equipment / operating conditions $79,000 $22,000 - - $157,000
-
gal
- $(-78,000.0) - -
03 3.1191: Change procedures / equipment / operating conditions $36,000 $600 - - $36,000
-
gal
- - - -
04 2.8113: Purchase gas directly from a contract gas supplier $7,000 - - - - - - $7,000 -
05 3.1161: Eliminate/reduce an operation $5,000 $9,000 - - - - - - $5,000
06 2.7124: Make a practice of turning off lights when not needed $1,000 - $1,000
14,654
kWh
- - - - - -
07 2.1233: Analyze flue gas for proper air/fuel ratio $500 $300 - $500
-
MMBtu
- - - - -
TOTAL RECOMMENDED $243,500 $171,900 $1,000
14,654
kWh
$500
-
MMBtu
$193,000
-
gal
$2,000
-
lb
$(-13,000.0) $55,000 $5,000
TOTAL IMPLEMENTED $80,500 $22,300 $1,000
14,654
kWh
$500
-
MMBtu
$157,000
-
gal
- $(-78,000.0) - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs