| Assessment Year | 1996 |
|---|---|
| Principal Product | Plastic Extrusion Molding |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 54 |
| Plant Area |
50,000
ft2
|
| Annual Production | 5,000,000
lb
|
| Production Hrs. Annual | 6,732
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $42,340 | 1,194,607 |
kWh
|
$0.035 |
| Electricity Demand | $25,963 | 3,134 |
kW-mo/yr
|
$8.28 |
| Electricity Fees | $1,144 | - |
|
- |
| Natural Gas | $6,907 | 1,057 |
MMBtu
|
$6.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,637 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $318 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.8314: Purchase high materials in returnable bulk containers | $18,480 | - | - | - |
$18,480
-
lb
|
- | - | - | - | |
| 02 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $3,578 | $4,440 |
$(-500.0)
(-16,706)
kWh
|
- | - | $(-5,712.0) | $(-200.0) | - | $9,990 | |
| 03 | 2.7144: Install spectral reflectors / delamp | $5,833 | $17,762 |
$2,971
99,062
kWh
|
$2,122
-
kW-mo/yr
|
- | - | - | $740 | - | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,428 | $4,000 | - |
$4,428
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $318 | $30 |
$158
5,275
kWh
|
$160
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $32,637 | $26,232 |
$2,629
87,631
kWh
|
$6,710
-
kW-mo/yr
|
$18,480
-
lb
|
$(-5,712.0) | $(-200.0) | $740 | $9,990 | ||
| TOTAL IMPLEMENTED | $318 | $30 |
$158
5,275
kWh
|
$160
-
kW-mo/yr
|
- | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs