ITAC Assessment: CL2007
ITAC logo
ITAC Assessment: CL2007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Capacitors
NAICS 334419: Other Electronic Component Manufacturing
SIC 3675: Electronic Capacitors
Sales Range $10
M
to 50
M
# of Employees 195
Plant Area 150,000
ft2
Annual Production 44,000,000
pieces
Production Hrs. Annual 4,200
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $327,100 5,928,000
kWh
Electricity Demand $155,545 11,669
kW-mo/yr
Natural Gas $45,502 6,123
MMBtu
Waste Disposal Costs
Water Usage $4,994 1,284
Tgal
Water Disposal $12,195 1,284
Tgal
TOTAL YEARLY COSTS $545,336
RECOMMENDED SAVINGS* $65,095 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,018

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,082 $10,098 $3,137
51,076
kWh
$1,945
-
kW-mo/yr
-
02 2.2511: Insulate bare equipment $936 $5,431 - - $936
-
MMBtu
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $58,440 $10,000 - $58,440
-
kW-mo/yr
-
04 2.6211: Conserve energy by efficient use of vending machines $637 $630 $637
10,618
kWh
- -
TOTAL RECOMMENDED $65,095 $26,159 $3,774
61,694
kWh
$60,385
-
kW-mo/yr
$936
-
MMBtu
TOTAL IMPLEMENTED $6,018 $15,529 $3,137
51,076
kWh
$1,945
-
kW-mo/yr
$936
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs