Assessment Year | 1996 |
---|---|
Principal Product | Alcoholic beverages |
NAICS |
n/a
|
SIC | 2085: Distilled and Blended Liquors |
Sales Range | greater than $500 M |
# of Employees | 100 |
Plant Area |
500,000
ft2
|
Annual Production | 13,000
Tgal
|
Production Hrs. Annual | 6,048
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $870,433 | 21,486,518 |
kWh
|
$0.041 |
Electricity Demand | $289,561 | 42,186 |
kW-mo/yr
|
$6.86 |
Natural Gas | $57,028 | 19,037 |
MMBtu
|
$3.00 |
Wood | $121,750 | 900,000 |
MMBtu
|
$0.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,295,710 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Wood Savings | Gaseous Waste Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1182: Make a new by-product | $3,153,280 | $5,059,000 | n/a |
$(-2,000,000.0)
(-76,923,213)
kWh
|
- | - | - |
$8,000,000
-
lb
|
$(-846,720.0) | $(-2,000,000.0) | - |
02 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $772,731 | $2,866,500 | n/a |
$870,433
21,486,518
kWh
|
- |
$(-29,180.0)
-
MMBtu
|
$(-68,522.0)
-
MMBtu
|
- | - | - | - |
03 | 3.1182: Make a new by-product | $329,700 | $7,300 | n/a | - | - | - | - | - | $(-37,800.0) | $(-30,000.0) | $397,500 |
04 | 2.2514: Cover open tanks | $19,440 | $25,100 | n/a | - | - | - |
$19,440
-
MMBtu
|
- | - | - | - |
05 | 2.3212: Optimize plant power factor | $10,799 | $27,000 | n/a | - |
$10,799
-
kW-mo/yr
|
- | - | - | - | - | - |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $9,760 | $3,885 | n/a |
$4,991
191,970
kWh
|
$4,769
-
kW-mo/yr
|
- | - | - | - | - | - |
TOTAL RECOMMENDED | $4,295,710 | $7,988,785 |
$(-1,124,576.0)
(-55,244,725)
kWh
|
$15,568
-
kW-mo/yr
|
$(-29,180.0)
-
MMBtu
|
$(-49,082.0)
-
MMBtu
|
$8,000,000
-
lb
|
$(-884,520.0) | $(-2,030,000.0) | $397,500 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Wood Savings | Gaseous Waste Savings | Personnel Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs