ITAC Assessment: TN0563
ITAC logo
ITAC Assessment: TN0563
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Vinyl-coated polyester fabrics
NAICS
n/a
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 100,000
ft2
Annual Production 15,000
thousand feet
Production Hrs. Annual 7,488
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $206,897 4,487,984
kWh
Natural Gas $102,348 30,343
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $758,586 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,610

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings By-product Production Savings
01 2.7144: Install spectral reflectors / delamp $8,547 $16,638 $7,721
189,332
kWh
- - - - $826 -
02 2.2136: Install / repair insulation on steam lines $816 $134 - $816
-
MMBtu
- - - - -
03 2.7144: Install spectral reflectors / delamp $3,191 - $3,191
78,546
kWh
- - - - - -
04 2.2122: Install / repair insulation on condensate lines $643 $245 - $643
-
MMBtu
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,115 $701 $2,115
33,411
kWh
- - - - - -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,625 $1,540 $1,625
32,532
kWh
- - - - - -
07 2.2511: Insulate bare equipment $303 $170 - $303
-
MMBtu
- - - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,313 - $1,313
25,205
kWh
- - - - - -
09 2.8113: Purchase gas directly from a contract gas supplier $10,235 - - $10,235
-
MMBtu
- - - - -
10 3.1182: Make a new by-product $664,104 $275,000 - - $8,350
-
lb
$(-163,939.0) - - $819,693
11 3.1182: Make a new by-product $45,294 $100,000 - - $5,010
-
lb
$(-25,000.0) - - $65,284
12 3.8314: Purchase high materials in returnable bulk containers $11,700 $10,200 - - $7,800
-
lb
$3,000 $900 - -
13 3.5315: Lease / purchase baler; sell cardboard to recycler $8,700 $8,480 - - - $(-2,080.0) - - $10,780
TOTAL RECOMMENDED $758,586 $413,108 $15,965
359,026
kWh
$11,997
-
MMBtu
$21,160
-
lb
$(-188,019.0) $900 $826 $895,757
TOTAL IMPLEMENTED $29,610 $29,383 $15,965
359,026
kWh
$1,119
-
MMBtu
$7,800
-
lb
$3,000 $900 $826 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs