ITAC Assessment: TN0556
ITAC logo
ITAC Assessment: TN0556
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Molded polyurethane frames, signs and headboards
NAICS
n/a
SIC 2431: Millwork
Sales Range $1
M
to 5
M
# of Employees 120
Plant Area 68,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 6,864
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,767 1,160,317
kWh
LPG $27,315 3,560
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $218,548 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $206,129

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (haz) Savings Primary Raw Material Savings
01 2.7243: Improve air circulation with destratification fans / other methods $3,874 $7,950 - $3,874
-
MMBtu
- -
02 2.7144: Install spectral reflectors / delamp $4,587 $18,500 $3,992
81,770
kWh
- - $595
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $660 $1,240 $660
7,327
kWh
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $374 $38 $374
4,396
kWh
- - -
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,298 - $3,298
-
kWh
- - -
06 3.7211: Modify material application methods $205,755 $81,770 - - $405
-
lb
$205,350
TOTAL RECOMMENDED $218,548 $109,498 $8,324
93,493
kWh
$3,874
-
MMBtu
$405
-
lb
$205,945
TOTAL IMPLEMENTED $206,129 $81,808 $374
4,396
kWh
- $405
-
lb
$205,350
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (haz) Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs