| Assessment Year | 1995 |
|---|---|
| Principal Product | Molded polyurethane frames, signs and headboards |
| NAICS |
n/a
|
| SIC | 2431: Millwork |
| Sales Range | $1 M to 5M |
| # of Employees | 120 |
| Plant Area |
68,000
ft2
|
| Annual Production | 1,000,000
lb
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $94,767 | 1,160,317 |
kWh
|
$0.082 |
| LPG | $27,315 | 3,560 |
MMBtu
|
$7.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $218,548 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $206,129 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $3,874 | $7,950 | - |
$3,874
-
MMBtu
|
- | - | |
| 02 | 2.7144: Install spectral reflectors / delamp | $4,587 | $18,500 |
$3,992
81,770
kWh
|
- | - | $595 | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $660 | $1,240 |
$660
7,327
kWh
|
- | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $374 | $38 |
$374
4,396
kWh
|
- | - | - | |
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,298 | - |
$3,298
-
kWh
|
- | - | - | |
| 06 | 3.7211: Modify material application methods | $205,755 | $81,770 | - | - |
$405
-
lb
|
$205,350 | |
| TOTAL RECOMMENDED | $218,548 | $109,498 |
$8,324
93,493
kWh
|
$3,874
-
MMBtu
|
$405
-
lb
|
$205,945 | ||
| TOTAL IMPLEMENTED | $206,129 | $81,808 |
$374
4,396
kWh
|
- |
$405
-
lb
|
$205,350 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (haz) Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs