ITAC Assessment: TN0516
ITAC logo
ITAC Assessment: TN0516
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Extruded rubber and plastic automotive weather stripping
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 560
Plant Area 190,000
ft2
Annual Production 720,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $838,506 16,665,006
kWh
Natural Gas $117,805 13,370
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $138,390 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $138,229

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6218: Turn off equipment when not in use $81,008 $114,200 $81,008
1,620,164
kWh
-
02 2.7224: Reduce space conditioning during non-working hours $24,983 $1,750 - $24,983
-
MMBtu
03 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $12,822 $26,900 $12,822
256,448
kWh
-
04 2.2511: Insulate bare equipment $14,244 $2,200 $14,244
284,877
kWh
-
05 2.6218: Turn off equipment when not in use $2,022 $3,735 $2,022
40,445
kWh
-
06 2.4221: Install compressor air intakes in coolest locations $1,597 $460 $1,597
31,946
kWh
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $952 $796 $952
19,050
kWh
-
08 2.2511: Insulate bare equipment $601 $430 $601
12,016
kWh
-
09 2.6212: Turn off equipment during breaks, reduce operating time $161 $345 $161
3,224
kWh
-
TOTAL RECOMMENDED $138,390 $150,816 $113,407
2,268,170
kWh
$24,983
-
MMBtu
TOTAL IMPLEMENTED $138,229 $150,471 $113,246
2,264,946
kWh
$24,983
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs