ITAC Assessment: TN0514
ITAC logo
ITAC Assessment: TN0514
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product fabric and finished socks
NAICS
n/a
SIC 2361: Girls', Children's, and Infants' Dresses, Blouses, and Shirts
Sales Range $100
M
to 500
M
# of Employees 635
Plant Area 350,000
ft2
Annual Production 6,000,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $601,012 12,115,182
kWh
Natural Gas $464,095 158,333
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,503 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $51,983

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1243: Use heat from boiler blowdown to preheat boiler feed water $28,698 $23,000 - $28,698
-
MMBtu
02 2.2511: Insulate bare equipment $6,641 $2,168 - $6,641
-
MMBtu
03 2.2136: Install / repair insulation on steam lines $3,001 $1,750 - $3,001
-
MMBtu
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $13,643 $2,700 $13,643
272,860
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,520 - $2,520
50,410
kWh
-
TOTAL RECOMMENDED $54,503 $29,618 $16,163
323,270
kWh
$38,340
-
MMBtu
TOTAL IMPLEMENTED $51,983 $29,618 $13,643
272,860
kWh
$38,340
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs