ITAC Assessment: TN0487
ITAC logo
ITAC Assessment: TN0487
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Round and square logs for log home c
NAICS
n/a
SIC 2491: Wood Preserving
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 20,000
ft2
Annual Production 250
pieces
Production Hrs. Annual 2,475
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,465 674,385
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,228 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,019

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,905 $1,320 $1,905
14,654
kWh
02 2.6212: Turn off equipment during breaks, reduce operating time $610 $1,010 $610
4,689
kWh
03 2.4231: Reduce the pressure of compressed air to the minimum required $419 - $419
3,224
kWh
04 2.4314: Use synthetic lubricant $114 - $114
879
kWh
05 2.3212: Optimize plant power factor $25,200 $8,300 $25,200
-
kWh
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $8,980 - $8,980
-
kWh
TOTAL RECOMMENDED $37,228 $10,630 $37,228
23,446
kWh
TOTAL IMPLEMENTED $2,019 $1,320 $2,019
15,533
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs