ITAC Assessment: NC0612
ITAC logo
ITAC Assessment: NC0612
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Exhaust system parts
NAICS 336390: Other Motor Vehicle Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 630,000
ft2
Annual Production 2,500,000
pieces
Production Hrs. Annual 2,500
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $409,571 6,428,000
kWh
Electricity Demand $130,352 23,345
kW-mo/yr
TOTAL YEARLY COSTS $539,923
RECOMMENDED SAVINGS* $101,708 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $59,348

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,709 $16,988 $3,040
47,947
kWh
$669
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $36,235 $215,800 $30,345
478,621
kWh
$5,890
-
kW-mo/yr
- -
03 2.7135: Install occupancy sensors $467 $150 $467
7,371
kWh
- - -
04 2.7124: Make a practice of turning off lights when not needed $14,909 $500 $14,909
235,152
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,028 $200 $3,252
51,300
kWh
$1,576
-
kW-mo/yr
$(-400.0) $(-400.0)
06 2.8114: Change rate schedules or other changes in utility service $42,360 $500 $42,360
-
kWh
- - -
TOTAL RECOMMENDED $101,708 $234,138 $94,373
820,391
kWh
$8,135
-
kW-mo/yr
$(-400.0) $(-400.0)
TOTAL IMPLEMENTED $59,348 $233,638 $52,013
820,391
kWh
$8,135
-
kW-mo/yr
$(-400.0) $(-400.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs