Assessment Year | 1990 |
---|---|
Principal Product | MEN SUITS & SPORT COATS |
NAICS |
n/a
|
SIC | 2311: Men's and Boys' Suits, Coats, and Overcoats |
Sales Range | $50 M to 100M |
# of Employees | 925 |
Plant Area |
n/a
|
Annual Production | 700,000
pieces
|
Production Hrs. Annual | 3,995
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $155,234 | 3,143,904 |
kWh
|
$0.049 |
Natural Gas | $86,111 | 24,048 |
MMBtu
|
$3.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,860 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,896 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $2,941 | $500 | - |
$2,941
-
MMBtu
|
- | |
02 | 2.7123: Keep lamps and reflectors clean | $11,964 | - |
$11,044
225,381
kWh
|
- | $920 | |
03 | 2.2136: Install / repair insulation on steam lines | $2,891 | $1,405 | - |
$2,891
-
MMBtu
|
- | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,019 | $3,000 | - |
$1,019
-
MMBtu
|
- | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $810 | - | - |
$810
-
MMBtu
|
- | |
06 | 2.2122: Install / repair insulation on condensate lines | $641 | $200 | - |
$641
-
MMBtu
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $862 | $480 |
$862
17,585
kWh
|
- | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $732 | - |
$732
14,947
kWh
|
- | - | |
TOTAL RECOMMENDED | $21,860 | $5,585 |
$12,638
257,913
kWh
|
$8,302
-
MMBtu
|
$920 | ||
TOTAL IMPLEMENTED | $9,896 | $5,585 |
$1,594
32,532
kWh
|
$8,302
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs