Assessment Year | 1990 |
---|---|
Principal Product | HOSIERY |
NAICS |
n/a
|
SIC | 2252: Hosiery, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 12,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $113,235 | 1,844,666 |
kWh
|
$0.061 |
Natural Gas | $25,947 | 5,186 |
MMBtu
|
$5.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,466 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,789 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $1,200 | $475 | - |
$1,200
-
MMBtu
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,431 | - |
$2,431
39,859
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $681 | $1,850 | - |
$681
-
MMBtu
|
|
04 | 2.2135: Repair and eliminate steam leaks | $429 | $190 | - |
$429
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,377 | $354 |
$1,377
22,567
kWh
|
- | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $948 | - |
$948
15,533
kWh
|
- | |
07 | 2.2122: Install / repair insulation on condensate lines | $211 | $482 | - |
$211
-
MMBtu
|
|
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $626 | $210 |
$626
10,258
kWh
|
- | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $317 | - |
$317
5,275
kWh
|
- | |
10 | 2.6212: Turn off equipment during breaks, reduce operating time | $246 | $635 |
$246
4,103
kWh
|
- | |
TOTAL RECOMMENDED | $8,466 | $4,196 |
$5,945
97,595
kWh
|
$2,521
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,789 | $3,561 |
$3,268
53,633
kWh
|
$2,521
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs