| Assessment Year | 1987 |
|---|---|
| Principal Product | SAUSAGE LINKS & PATTIES |
| NAICS |
n/a
|
| SIC | 2011: Meat Packing Plants |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
n/a
|
| Annual Production | 13,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $97,661 | 1,851,993 |
kWh
|
$0.053 |
| LPG | $25,886 | 3,307 |
MMBtu
|
$7.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,178 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,961 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $10,904 | $421 |
$3,122
58,910
kWh
|
$7,782
-
MMBtu
|
- | |
| 02 | 2.2163: Use minimum steam operating pressure | $2,633 | - | - |
$2,633
-
MMBtu
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,019 | $5,000 |
$2,019
38,101
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,134 | $90 |
$1,134
21,395
kWh
|
- | - | |
| 05 | 2.2135: Repair and eliminate steam leaks | $849 | $75 | - |
$849
-
MMBtu
|
- | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $218 | - | - |
$518
-
MMBtu
|
$(-300.0) | |
| 07 | 2.2511: Insulate bare equipment | $204 | $50 | - |
$204
-
MMBtu
|
- | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $217 | - |
$217
4,103
kWh
|
- | - | |
| TOTAL RECOMMENDED | $18,178 | $5,636 |
$6,492
122,509
kWh
|
$11,986
-
MMBtu
|
$(-300.0) | ||
| TOTAL IMPLEMENTED | $17,961 | $5,636 |
$6,275
118,406
kWh
|
$11,986
-
MMBtu
|
$(-300.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs