Assessment Year | 1987 |
---|---|
Principal Product | SAUSAGE LINKS & PATTIES |
NAICS |
n/a
|
SIC | 2011: Meat Packing Plants |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 13,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,661 | 1,851,993 |
kWh
|
$0.053 |
LPG | $25,886 | 3,307 |
MMBtu
|
$7.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,178 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,961 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $10,904 | $421 |
$3,122
58,910
kWh
|
$7,782
-
MMBtu
|
- | |
02 | 2.2163: Use minimum steam operating pressure | $2,633 | - | - |
$2,633
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,019 | $5,000 |
$2,019
38,101
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,134 | $90 |
$1,134
21,395
kWh
|
- | - | |
05 | 2.2135: Repair and eliminate steam leaks | $849 | $75 | - |
$849
-
MMBtu
|
- | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $218 | - | - |
$518
-
MMBtu
|
$(-300.0) | |
07 | 2.2511: Insulate bare equipment | $204 | $50 | - |
$204
-
MMBtu
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $217 | - |
$217
4,103
kWh
|
- | - | |
TOTAL RECOMMENDED | $18,178 | $5,636 |
$6,492
122,509
kWh
|
$11,986
-
MMBtu
|
$(-300.0) | ||
TOTAL IMPLEMENTED | $17,961 | $5,636 |
$6,275
118,406
kWh
|
$11,986
-
MMBtu
|
$(-300.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs