| Assessment Year | 1986 |
|---|---|
| Principal Product | PORCELAIN ENAMEL |
| NAICS |
n/a
|
| SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
n/a
|
| Annual Production | 41,400,000
lb
|
| Production Hrs. Annual | 5,880
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $569,347 | 11,645,956 |
kWh
|
$0.049 |
| Natural Gas | $854,056 | 173,933 |
MMBtu
|
$4.91 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $156,413 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $69,413 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $80,968 | $70,000 | - |
$80,968
-
MMBtu
|
|
| 02 | 2.2443: Re-use or recycle hot or cold process exhaust air | $42,615 | $46,000 | - |
$42,615
-
MMBtu
|
|
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $23,107 | $20,800 |
$23,107
471,571
kWh
|
- | |
| 04 | 2.6242: Minimize operation of equipment maintained in standby condition | $6,032 | $1,810 |
$6,032
123,095
kWh
|
- | |
| 05 | 2.2511: Insulate bare equipment | $3,691 | $492 |
$3,691
75,322
kWh
|
- | |
| TOTAL RECOMMENDED | $156,413 | $139,102 |
$32,830
669,988
kWh
|
$123,583
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $69,413 | $67,292 |
$26,798
546,893
kWh
|
$42,615
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs