ITAC Assessment: TN0293
ITAC logo
ITAC Assessment: TN0293
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product RUBBER O-RINGS
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 450
Plant Area
n/a
Annual Production 390,000,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $262,860 5,056,858
kWh
Natural Gas $135,266 22,780
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,188 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,981

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $13,716 $2,811 - $13,716
-
MMBtu
02 2.2515: Use optimum thickness insulation $1,969 $500 - $1,969
-
MMBtu
03 2.7111: Reduce illumination to minimum necessary levels $3,536 - $3,536
67,995
kWh
-
04 2.4239: Eliminate or reduce compressed air usage $1,798 $500 $1,798
34,584
kWh
-
05 2.6218: Turn off equipment when not in use $640 - $640
12,309
kWh
-
06 2.6218: Turn off equipment when not in use $625 $500 $625
12,016
kWh
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $625 $180 $625
12,016
kWh
-
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,279 $300 $1,279
24,619
kWh
-
TOTAL RECOMMENDED $24,188 $4,791 $8,503
163,539
kWh
$15,685
-
MMBtu
TOTAL IMPLEMENTED $14,981 $2,991 $1,265
24,325
kWh
$13,716
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs