ITAC Assessment: TN0284
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product HAMBURGER & HOT DOG BUNS
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 103
Plant Area
n/a
Annual Production 25,000,000
lb
Production Hrs. Annual 7,280
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $113,471 2,432,884
kWh
Natural Gas $160,152 28,168
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,920 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,920

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings
01 2.2136: Install / repair insulation on steam lines $8,573 $1,383 $8,573
-
MMBtu
02 2.2444: Use hot process fluids to preheat incoming process fluids $8,026 $14,300 $8,026
-
MMBtu
03 2.2122: Install / repair insulation on condensate lines $1,112 $195 $1,112
-
MMBtu
04 2.2122: Install / repair insulation on condensate lines $707 $104 $707
-
MMBtu
05 2.6241: Reduce temperature of process equipment when on standby $422 $800 $422
-
MMBtu
06 2.1233: Analyze flue gas for proper air/fuel ratio $80 $300 $80
-
MMBtu
TOTAL RECOMMENDED $18,920 $17,082 $18,920
-
MMBtu
TOTAL IMPLEMENTED $18,920 $17,082 $18,920
-
MMBtu
Yearly Savings* Imp'd Cost* Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs