ITAC Assessment: TN0283
ITAC logo
ITAC Assessment: TN0283
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product FLEXIBLE TUBE PACKAGING
NAICS
n/a
SIC 3084: Plastics Pipe
Sales Range $50
M
to 100
M
# of Employees 525
Plant Area
n/a
Annual Production 770,000
thousand feet
Production Hrs. Annual 8,400
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $828,547 19,691,091
kWh
Natural Gas $41,761 9,207
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $66,950 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $50,197

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4322: Use or replace with energy efficient substitutes $31,143 $20,000 $31,143
741,501
kWh
02 2.7111: Reduce illumination to minimum necessary levels $15,904 - $15,904
378,664
kWh
04 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $13,182 $940 $13,182
313,892
kWh
05 2.2511: Insulate bare equipment $3,742 $660 $3,742
89,097
kWh
06 2.6212: Turn off equipment during breaks, reduce operating time $2,130 $2,600 $2,130
50,703
kWh
07 2.2511: Insulate bare equipment $849 $276 $849
20,223
kWh
TOTAL RECOMMENDED $66,950 $24,476 $66,950
1,594,080
kWh
TOTAL IMPLEMENTED $50,197 $24,200 $50,197
1,195,193
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs