ITAC Assessment: TN0243
ITAC logo
ITAC Assessment: TN0243
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product SENSORS FOR COMPUTERS
NAICS
n/a
SIC 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area
n/a
Annual Production 8,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $19,942 342,028
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,198 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,907

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7111: Reduce illumination to minimum necessary levels $1,386 - $1,386
23,740
kWh
02 2.6212: Turn off equipment during breaks, reduce operating time $615 - $615
10,551
kWh
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $906 $30 $906
15,533
kWh
04 2.2511: Insulate bare equipment $291 $200 $291
4,982
kWh
TOTAL RECOMMENDED $3,198 $230 $3,198
54,806
kWh
TOTAL IMPLEMENTED $2,907 $30 $2,907
49,824
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs