ITAC Assessment: TN0241
ITAC logo
ITAC Assessment: TN0241
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product WARMUP SUITS
NAICS
n/a
SIC 2339: Women's, Misses', and Juniors' Outerwear, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 200
Plant Area
n/a
Annual Production 250,000
pieces
Production Hrs. Annual 2,142
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $13,755 249,121
kWh
Natural Gas $6,929 1,116
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,128 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $227

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7111: Reduce illumination to minimum necessary levels $1,752 - $1,752
31,653
kWh
-
02 2.7243: Improve air circulation with destratification fans / other methods $149 $1,000 - $149
-
MMBtu
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $162 - $162
2,931
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $65 - $65
1,172
kWh
-
TOTAL RECOMMENDED $2,128 $1,000 $1,979
35,756
kWh
$149
-
MMBtu
TOTAL IMPLEMENTED $227 - $227
4,103
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs